Golden State Water Co. to begin pipeline replacement project

CLEARLAKE, Calif. – On Wednesday Golden State Water Co. will break ground on a new $418,600 pipeline replacement project as part of its infrastructure improvement plan for its Clearlake Customer Service Area.

The project involves installing 2,175 feet of new 8-inch diameter pipeline at San Joaquin Avenue east of the intersection of Lakeshore Drive at Island Drive, proceeding east to Parkview Drive and Park Terrace Drive at 12480 San Joaquin Ave., the company reported.

Existing 2-inch steel water mains that are more than 50 years old will be replaced with new polyvinyl chloride pipe (PVC), Golden State Water said.

The company said the replacement project will result in reduced leaks and improved fire protection for the Clearlake Customer Service Area.

In addition to this project, which was budgeted in a previous year, Golden State is authorized to invest another $480,000 in local improvements in 2012. More information about these projects is available at www.gswater.com/csa_homepages/clearlake.html.

“This project is one of several scheduled in our Clearlake Water System this year to help us maintain our critical infrastructure for our customers,” said Golden State Water Company District Manager Paul Schubert.

Golden State believes that proactive system maintenance is critical to protecting water service now and for future generations. Delaying or deferring needed improvements can be more costly and jeopardize water quality.

The work will consist of cutting through the existing concrete to remove the older pipeline and to install the new one.

The streets will remain open to traffic during the construction period but traffic and parking may be restricted during the working hours. The construction crews will make every effort to keep dust to a minimum.

Residents may experience periods with an increased level of noise during construction. Weekly activities such as trash pickup will not be interrupted.
The work is scheduled to last up to 45 days. Normal water service will not be interrupted except as needed to connect the new water mains to the existing system.

Customers will receive advance notification if their service will be temporarily interrupted.

Customers with questions about the project can call Golden State’s 24-hour Customer Service Center at 800-999-4033.

Follow Lake County News on Twitter at http://twitter.com/LakeCoNews, on Tumblr at www.lakeconews.tumblr.com, on Google+, on Facebook at www.facebook.com/pages/Lake-County-News/143156775604?ref=mf and on YouTube at www.youtube.com/user/LakeCoNews .

Upcoming Calendar

1May
05.01.2024 4:00 pm - 5:30 pm
East Region Town Hall
1May
05.01.2024 5:30 pm - 7:30 pm
Homelessness and Mental Health Resource Fair
2May
05.02.2024 5:00 pm - 8:00 pm
Neighborfest
4May
05.04.2024 2:00 pm - 4:00 pm
Park Study Club afternoon tea
5May
05.05.2024
Cinco de Mayo
6May
05.06.2024 11:00 am - 4:00 pm
Senior Summit
12May
05.12.2024
Mother's Day
27May
05.27.2024
Memorial Day

Mini Calendar

loader

LCNews

Award winning journalism on the shores of Clear Lake. 

 

Newsletter

Enter your email here to make sure you get the daily headlines.

You'll receive one daily headline email and breaking news alerts.
No spam.