Friday, 03 May 2024

Caltrans plans major roadwork through July 28

NORTH COAST, Calif. – Caltrans reports that the following road projects will be taking place around Lake County and the North Coast during the coming week.

Included are Mendocino County projects that may impact Lake County commuters.

LAKE COUNTY

Highway 20

– Pavement repairs from Sayre Avenue to the Paradise Cove subdivision will continue. One-way traffic control will be in effect between 8 p.m. and 5 a.m., weeknights. One-way traffic control will also be in effect from 7 a.m. to 4 p.m. weekdays. Motorists should anticipate 10-minute delays.

– The Mine Restoration Project has been issued a long-term Caltrans Encroachment Permit to allow trucks to access their worksite near the Colusa County Line. Traffic will be restricted to one lane in each direction from 7 a.m. to 9 a.m. Motorists should anticipate minor traffic slowdowns.
 
Highway 29

– Valley fire recovery work between Middletown and Hidden Valley will continue. One-way traffic control will be in effect from 7 a.m. to 7 p.m., weekdays. Motorists should anticipate 15-minute delays.

Highway 175

– Valley fire recovery work between Middletown and Loch Lomond will continue. One-way traffic control will be in effect from 7 a.m. to 7 p.m., weekdays. Motorists should anticipate 15-minute delays.
 
MENDOCINO COUNTY

Highway 1

– Paving between Pacific View Drive and Irish Beach Drive will begin Monday, July 25. One-way traffic control will be in effect from 7 a.m. to 6 p.m., weekdays. Motorists should anticipate 15-minute delays.

– Paving between Lille Lake Road and Happy Lane will begin Wednesday, July 27. One-way traffic control will be in effect from 7 a.m. to 3 p.m., weekdays. Motorists should anticipate 15-minute delays.

– Highway repairs a quarter-mile north of Ocean Meadows Circle will continue. One-way traffic control with a temporary signal will be in effect 24 hours per day, seven days per week. Motorists should anticipate five-minute delays.

– Paving between Road 430 and the Georgia Pacific Picnic Area will begin Thursday, July 28. One-way traffic control will be in effect from 7 a.m. to 3 p.m., weekdays. Motorists should anticipate 15-minute delays.

Highway 20

– Paving operations between Summer Lane and the Blosser Road will continue. One-way traffic control will be in effect from 7 a.m. to 3 p.m., weekdays. Motorists should anticipate 15-minute delays.

– Paving operations from just east of Gino’s to just west of Old Bard will begin Tuesday, July 26. One-way traffic control will be in effect from 8 a.m. to 5 p.m., weekdays. Motorists should anticipate 15-minute delays.

Highway 101

– Digouts and paving work between the Hollands Lane and the end of Main Street will continue. One-way traffic control will be in effect overnight from 7 p.m. to 7 a.m. Motorists should anticipate 15-minute delays.

– The city of Willits has been granted a Caltrans Encroachment Permit to repair a water main between Sherwood Road and Casteel Lane beginning Thursday, July 21. Traffic will be restricted to one lane in each direction from 8 a.m. to 4 p.m. Motorists may experience minor traffic slowdowns.

– Paving operations between Old Sherwood Road and Rattlesnake Creek will continue. One-way traffic control will be in effect from 7 a.m. to 5 p.m., weekdays. Motorists should anticipate 15-minute delays.

– The Enchanted Forest Event has been granted a Caltrans Encroachment Permit provide access to the event at Black Oaks Ranch. An extended left-turn lane will be in place between Thursday, July 21, and Monday, July 25. Motorists should anticipate 10-minute delays.

– Emergency slide repairs just south of Standish-Hickey State Park will continue. One-way traffic control with a temporary signal will be in effect 24 hours per day, seven days per week. Motorists should anticipate five-minute delays.

Highway 128

– Drainage work from Masonite Timber to approximately 1.8 miles east of the junction with Route 1 will continue. One-way traffic control will be in effect from 7 a.m. to 5 p.m. Motorists should anticipate 10-minute delays.

– AT&T has been granted a Caltrans Encroachment Permit to perform utility work near Greenwood Road just outside Philo. One-way traffic control will be in effect from 8 a.m. to 3 p.m. weekdays. Motorists should anticipate five-minute delays.

Highway 162

– Paving operations between East Lane Road and Short Creek will continue. One-way traffic control will be in effect from 7 a.m. to 6 p.m. Motorists should anticipate 10-minute delays.

– Paving operations between East Lane Road and the Long Valley Creek Bridge will continue. One-way traffic control will be in effect from 7 a.m. to 3 p.m. Motorists should anticipate 10-minute delays.

– The Round Valley Indian Tribe has been granted a Caltrans Encroachment Permit to pave a driveway near Barnes Lane. One-way traffic control will be in effect from 7 a.m. to 3 p.m., weekdays. Motorists should anticipate five-minute delays.

Highway 253

– Highway repairs from Cattle Pass to Butler Ranch will continue. One-way traffic control with a temporary signal will be in effect from 7 a.m. to 5 p.m. weekdays. Motorists should anticipate 10-minute delays.

The Caltrans Traffic Operations Office has reviewed each project and determined that individual project delays are expected to be less than the statewide policy maximum of 30 minutes, unless noted otherwise above.

For information pertaining to emergency roadwork or for updates to scheduled roadwork, please contact the California Highway Information Network (CHIN) at 1-800-GAS-ROAD (1-800-427-7623).

Upcoming Calendar

4May
05.04.2024 2:00 pm - 4:00 pm
Park Study Club afternoon tea
5May
05.05.2024
Cinco de Mayo
6May
05.06.2024 11:00 am - 4:00 pm
Senior Summit
8May
05.08.2024 6:30 pm - 7:30 pm
Fire preparedness town hall
12May
05.12.2024
Mother's Day
27May
05.27.2024
Memorial Day
14Jun
06.14.2024
Flag Day
16Jun
06.16.2024
Father's Day
19Jun
06.19.2024
Juneteenth

Mini Calendar

loader

LCNews

Award winning journalism on the shores of Clear Lake. 

 

Newsletter

Enter your email here to make sure you get the daily headlines.

You'll receive one daily headline email and breaking news alerts.
No spam.