Major road reconstruction begins in Clearlake next week

Print
CLEARLAKE – One of the largest street-repair projects in Clearlake's history is getting under way. {sidebar id=65}


A $3.1 million project to reconstruct parts of Lakeshore, Old Highway 53 and a portion of Burns Valley Road is set to begin April 21, city officials said this week.


“I've issued the notice to proceed and they're out marking the streets now,” City Administrator Dale Neiman said Thursday.


The project, which Neiman said is the largest contract the city has ever awarded, will be funded by state transportation funds and Proposition 1B bond money.


Thanks to early preparation, City Engineer Bob Galusha helped land the money, said Neiman. In fact, Clearlake was the first agency in the state to receive funds from the bond.


The project, the contract for which was awarded earlier this year, was bid during the winter, which is the best time to get a good contract rate, because contractors are lining up work for the season, said Neiman. The slowing economy and less construction projects also helped get a better price, he added.


The result, was that the project – originally estimated to cost $2.9 million – came in at less than $1.4 million. Asphalt prices in the bid were in the range of $70 per ton, as opposed to $140 per ton, which was the price for asphalt in the 2005 midtown overlay project, Neiman said.


The city had hoped to be able to use the leftover $1.5 million on other roads in the city, said Neiman, including Pomo, Arrowhead, Park and Lakeshore Drive starting at City Hall and going west and east for as long as the funds would last.


However, Caltrans said that plan wouldn't work because, according to its funding regulations, the area included in the project had to be contiguous, said Neiman.


So, rather than go back to the state with new plans and risk losing the money, Neiman said they'll adapt.


The plans call for starting work at the senior center on Burns Valley and moving toward, and continuing along, Old Highway 53, said Neiman. Sections of Olympic Drive not completed in the past will be done. The project also will move from Lakeshore Drive at Highway 53 and move as far down as possible.


“We think we might make it almost to City Hall,” said Neiman.


City officials reported that the project will necessitate some road closures, but alternate routes will be offered. Flaggers will help direct traffic, and there will be advance signs and handout fliers with work and traffic information that will detail dates, times and durations of planned closures.


The project's contractor is Central Valley Paving and Asphalt of Roseville.


When the work is done, said Neiman, the streets in the project area will be “brand new.”


E-mail Elizabeth Larson at This email address is being protected from spambots. You need JavaScript enabled to view it..


{mos_sb_discuss:3}