Third Street improvements begin Monday

LAKEPORT – The city of Lakeport's Third Street and City Hall parking lot improvement project is getting under way on Monday.


City Engineer Scott Harter reports that the project limits will be on Third Street, directly east of Main Street to the east side of Park Street, and the parking lot adjacent to City Hall.


FEDCO Construction began mobilizing and performing preparatory work last week, according to Harter.


Construction is expected to last 11 weeks, during which Third Street will remain open with the exception of 12 days for removal and repaving operations.


Harter said all affected businesses – The Ink Spot, On the Waterfront and Park Place restaurant – will remain open during construction. Alternative vehicle access for businesses on the north side of Third Street and the Third Street boat ramp is via Fourth Street and the waterfront parking lot.


Alternate vehicle access to The Ink Spot is via Second Street along the alleyway between Main and Park Streets, according to Harter.


Questions may be directed to Harter at 263-5614, extension 11.


{mos_sb_discuss:2}

Upcoming Calendar

27Apr
04.27.2024 7:00 pm - 9:00 pm
Inaugural Team Trivia Challenge
2May
05.02.2024 5:00 pm - 8:00 pm
Neighborfest
4May
05.04.2024 2:00 pm - 4:00 pm
Park Study Club afternoon tea
5May
05.05.2024
Cinco de Mayo
6May
05.06.2024 11:00 am - 4:00 pm
Senior Summit
12May
05.12.2024
Mother's Day
27May
05.27.2024
Memorial Day
14Jun
06.14.2024
Flag Day

Mini Calendar

loader

LCNews

Award winning journalism on the shores of Clear Lake. 

 

Newsletter

Enter your email here to make sure you get the daily headlines.

You'll receive one daily headline email and breaking news alerts.
No spam.