Caltrans plans major roadwork through June 2

NORTH‌‌ ‌‌COAST, ‌‌ ‌‌Calif. —‌ Caltrans‌‌ ‌‌reports‌‌ ‌‌that‌‌ ‌‌the‌‌ ‌‌following‌‌ ‌‌road‌‌ ‌‌projects‌‌ ‌‌will‌‌ ‌‌be‌‌ ‌‌taking‌‌ ‌‌place‌‌ ‌‌‌around‌‌ ‌‌the‌‌ ‌‌North‌‌ ‌‌Coast‌‌ ‌‌during‌‌ ‌‌the‌‌ ‌‌coming‌‌ ‌‌week. ‌‌ ‌‌‌ ‌
‌‌‌ ‌
Included‌‌ ‌‌are‌‌ ‌‌Mendocino‌‌ ‌‌County‌‌ ‌‌projects‌‌ ‌‌that‌‌ ‌‌may‌‌ ‌‌impact‌‌ ‌‌Lake‌‌ ‌‌County‌‌ ‌‌commuters, as well as work in Del Norte and Humboldt counties.
‌‌‌ ‌
Caltrans‌‌ ‌‌advises‌‌ ‌‌motorists‌‌ ‌‌to‌‌ ‌‌drive‌‌ ‌‌with‌‌ ‌‌caution‌‌ ‌‌when‌‌ ‌‌approaching‌‌ ‌‌work‌‌ ‌‌areas‌‌ ‌‌and‌‌ ‌‌to‌‌ ‌‌be‌‌ ‌‌‌prepared‌‌ ‌‌to‌‌ ‌‌stop‌‌ ‌‌at‌‌ ‌‌traffic‌‌ ‌‌control‌‌ ‌‌stations. ‌‌ ‌‌‌ ‌
‌‌‌ ‌
The‌‌ ‌‌Caltrans‌‌ ‌‌Traffic‌‌ ‌‌Operations‌‌ ‌‌Office‌‌ ‌‌has‌‌ ‌‌reviewed‌‌ ‌‌each‌‌ ‌‌project‌‌ ‌‌and‌‌ ‌‌determined‌‌ ‌‌that‌‌ ‌‌individual‌‌ ‌‌‌project‌‌ ‌‌delays‌‌ ‌‌are‌‌ ‌‌expected‌‌ ‌‌to‌‌ ‌‌be‌‌ ‌‌less‌‌ ‌‌than‌‌ ‌‌the‌‌ ‌‌statewide‌‌ ‌‌policy‌‌ ‌‌maximum‌‌ ‌‌of‌‌ ‌‌30‌‌ ‌‌minutes‌‌ ‌‌unless‌‌ ‌‌‌ ‌noted‌‌ ‌‌otherwise. ‌‌ ‌‌‌ ‌‌‌ ‌

Caltrans will suspend most work on Northern California highways from Friday, May 27, through Monday, May 30, in observance of Memorial Day weekend. However, in the case of unforeseen circumstances, it may be necessary for Caltrans crews to respond to emergency situations.

For‌‌ ‌‌updates‌‌ ‌‌to‌‌ ‌‌this‌‌ ‌‌list‌‌ ‌‌check‌‌ ‌‌QuickMap‌‌ ‌‌at‌‌ ‌‌‌www.dot.ca.gov‌‌‌ or‌‌ ‌‌1-800-GAS-ROAD‌‌ ‌‌‌(1-800-427-7623). ‌‌ ‌‌‌ ‌

LAKE‌‌ ‌‌COUNTY‌‌ ‌‌‌ ‌
‌‌‌ ‌
Highway‌‌ ‌‌29

— Road work continues near Hidden Valley Lake at Spruce Grove Road. Lane closures will be in effect from 7 a.m. to 5 p.m. weekdays. Motorists should expect five-minute delays.

MENDOCINO COUNTY

Highway 1

— Emergency Road work continues in Westport from Blue Slide Gulch to Pacific Avenue. Lane closures will be in effect from 8 a.m. to 4 p.m. Motorists should expect five-minute delays.

Highway 20

— Guardrail work in Willits west of the 101 Jct will continue. One-way traffic control will be in place from 6 a.m. to 5 p.m. weekdays. Motorists should expect up to 10-minute delays.

Highway 101

— Slide removal at Pieta Creek Bridge will continue. Northbound Lane closures will be in effect. Motorists should anticipate five-minute delays.

— Fence work at the East Perkins Street Overcrossing in Ukiah will begin on Tuesday, May 31. Lane closures will be in effect from 6:30 a.m. to 6:00 p.m. weekdays. Motorists should expect minor slowdowns through the area.

— Moss Cove Safety Rest Area will be closed through July 2022.

— Empire Camp Safety Rest Area will be closed through July 2022.

Highway 162

— Road work south of Dos Rios near the Rodeo Creek Bridge continues. One-way traffic control will be in effect from 3 p.m. to 7 a.m. weeknights. Motorists should expect up to 10-minute delays.

Highway 271

— Slide removal continues south of Piercy near Reynolds State Park Road. A lane closure is in effect and motorists should use an alternate route.

DEL NORTE COUNTY

Highway 101

— Construction work from the Route 169 junction to north of Klamath will continue. One-way traffic control will be in effect from 7 a.m. to 3 p.m. Motorists should anticipate 10-minute delays.

— Bridge work north of Klamath near Old Hunter Creek Road will continue. One-way traffic control will be in effect. Motorists should anticipate 10-minute delays.

— Construction in the Last Chance Grade area will continue. One-way traffic control will be in effect. Motorists should anticipate 25-minute delays at all hours.

— Bridge work at Rowdy Creek will continue. One-way traffic control will be in effect weekdays. Motorists should anticipate minor slowdowns.

Highway 199

— Construction work near Kings Valley Road will begin on Tuesday, May 31. One-way traffic control will be in effect weekdays. Motorists should anticipate 10-minute delays.

— Bridge work at Hiouchi Bridge will continue. One-way traffic control will be in effect weekdays. Motorists should anticipate minor slowdowns.

— Permitted cleanup and repair work between Hiouchi and Gasquet will continue. One-way traffic control will be in effect weekdays from 7 a.m. to 5 p.m. Motorists should anticipate five-minute delays.

— Bridge work from Mary Adam Peacock Bridge to Wagon Wheel Cafe will continue. One-way traffic control will be in effect weekdays. Motorists should anticipate minor slowdowns.

— Bridge work at Middle Fork Smith River Bridge will continue. One-way traffic control will be in effect weekdays. Motorists should anticipate minor slowdowns.

HUMBOLDT COUNTY

Highway 36

— Permitted utility work 1.5 miles west of Abe Wouk Memorial Grove Road will occur on Wednesday, June 1. One-way traffic control will be in effect from 7 a.m. to 5 p.m. Motorists should anticipate five-minute delays.

— Permitted utility work at Private Road will occur on Thursday, June 2. One-way traffic control will be in effect from 7 a.m. to 5 p.m. Motorists should anticipate five-minute delays.

— Construction work from Buck Mountain Road to the Trinity County line will continue. One-way traffic control will be in effect weekdays from 7 a.m. to 7 p.m. Motorists should anticipate 10-minute delays.

— Bridge work south of Phillipsville will continue. Lane closures will be in effect weekdays. Motorists should anticipate minor traffic slowdowns. A northbound onramp closure will also be in effect. Motorists should use an alternate route.

— Part of The Kinetic Grand Championship will take place on Sunday, May 29. A lane closure between the Herrick Avenue Overcrossing and Tompkins Hill Road will be in effect from 9 a.m. to 8 p.m. Motorists should anticipate five-minute delays.

— Construction from the Herrick Avenue Overcrossing to Washington Street in Eureka will continue. Lane closures will be in effect in both directions from 8 p.m. to 6 a.m. weeknights. A full lane closure is currently in effect at Washington Street. Motorists should anticipate 10-minute delays.

— Construction from the St Louis Road Overcrossing to Mad River Bridge will continue. Lane closures will be in effect from 8 p.m. to 6 a.m. Motorists should anticipate 10-minute delays. Starting May 31 at 9 p.m. a full ramp closure will be in effect at the Route 101/299 Junction. Motorists should choose an alternative route.

— Construction work from Murray Road Overcrossing to Georgia Pacific Road will begin on Tuesday, May 31. One-way traffic control will be in effect weekdays from 7 a.m. to 7 p.m. Motorists should anticipate 10-minute delays.

Highway 169

— Permitted utility at Private Road will occur on Friday, June 3. One-way traffic will be in effect from 7 a.m. to 5 p.m. Motorists should expect five-minute delays.

Highway 211

— Part of The Kinetic Grand Championship will take place on Monday, May 30. A full closure between Ocean Avenue and Eel River Drive will be in effect from 9 a.m. to 6 p.m. Motorists should anticipate five-minute delays.

Highway 254

— Permitted utility work south of Bear Creek Bridge will occur on Thursday, June 2. One-way traffic will be in effect from 8 a.m. to 4 p.m. Motorists should expect five-minute delays.

Highway 255

— Part of The Kinetic Grand Championship will take place on Saturday, May 28. One-way traffic control between Jackson Ranch Road and Dean Avenue will be in effect from 9 a.m. to 8 p.m. Motorists should anticipate 10-minute delays.

— Permitted utility work between K and V streets will begin on Wednesday, May 1. One-way traffic will be in effect from 7 a.m. to 6 p.m. weekdays. A full closure will also be in effect at the K Street intersection. Motorists should expect minor traffic slowdowns.

Highway 299

— Construction near Route 200 will continue. Lane closures will be in effect from 7 a.m. to 6 p.m. weekdays. Motorists should expect minor traffic slowdowns.

— Paving east of Blue Lake will continue. The westbound offramp at the Truck Scale House will be closed. Motorists should use an alternate ramp.

— Construction east of the Burney Vista Point will continue. Motorists should anticipate five-minute delays.

Upcoming Calendar

25Apr
04.25.2024 1:30 pm - 7:30 pm
FireScape Mendocino workshop
27Apr
04.27.2024 10:00 am - 2:00 pm
Prescription Drug Take Back Day
27Apr
04.27.2024 10:00 am - 2:00 pm
Northshore Ready Fest
27Apr
04.27.2024 7:00 pm - 9:00 pm
Inaugural Team Trivia Challenge
2May
05.02.2024 5:00 pm - 8:00 pm
Neighborfest
4May
05.04.2024 2:00 pm - 4:00 pm
Park Study Club afternoon tea
5May
05.05.2024
Cinco de Mayo
6May
05.06.2024 11:00 am - 4:00 pm
Senior Summit
12May
05.12.2024
Mother's Day

Mini Calendar

loader

LCNews

Award winning journalism on the shores of Clear Lake. 

 

Newsletter

Enter your email here to make sure you get the daily headlines.

You'll receive one daily headline email and breaking news alerts.
No spam.